How to read a sprint burndown chart
A burndown chart shows how much work is left in a sprint, day by day. It is one of the quickest ways to see whether the team will reach its goal, if you know what to look for.
What the chart shows
The horizontal axis is the days of the sprint. The vertical axis is the work remaining, usually in story points. A straight line from the starting total down to zero is the ideal pace. A second line shows the real remaining work, updated as stories are finished.
What the patterns mean
- Real line close to the ideal line: you are on track.
- Flat at the start, then a drop: work is started but not finished. Stories may be too big, or the team is working on many things at once.
- Real line above the ideal line: you are behind. Decide early what to cut or ask for help.
- Line goes up: work was added to the sprint. Check that it was a conscious choice.
- A cliff at the very end: stories are being finished at the last minute, which leaves no time for review or testing.
What to do about it
- Talk about it at the daily standup the moment the line starts to drift, not at the end of the sprint.
- Split large stories so that work finishes every day, not all at once.
- Limit work in progress. Finishing one thing is better than starting three.
- If the goal is at risk, agree with the product owner what to drop.
Use it as a conversation, not a score
A burndown chart does not judge the team. It helps the team notice problems early, while they are still cheap to fix. Look at it together every day, and use the retrospective to talk about patterns across sprints.